CWM integration with Project Workspace

On this page

CWM integration with Project Workspace

View and manage project tasks alongside CWM work without switching applications. Team members can see assigned project tasks, break down work, and manage connections while project managers track execution in Project Workspace.

The Project Workspace integration with Collaborative Work Management (CWM) gives project managers and team members a shared view of work across both applications. Team members work inside CWM using Boards and My Work. Project managers track that same work inside Project Workspace.

Each CWM task or story can be linked to a project and a project task.

Enabling the integration

Both applications must be installed and active in your instance to use the integration.

When both are active, the Project and Project task fields are available on CWM task records. The related row context menu options, such as Add child CWM task and Add child story, also are available in the List view.

Bring project tasks onto a Board

If a project task isn’t already on your Board, you can add it as connected work. For the steps, see Connect work from other ServiceNow apps to CWM Boards.

Adding a project task to a Board doesn’t bring across the CWM tasks or stories that are already linked to that project task. Each Board can have its own set of connected work items for the same project task. In Project Workspace, all of these connected items appear together under the project task.

How the integration supports collaborative work

The integration is designed so that team members and project managers can work in their preferred tools without losing visibility into each other’s activity.

  • Stay in CWM for daily work

    Create, update, and move CWM tasks and stories linked to a project task from Boards, list views, and My Work. You can also see which project task each work item supports without opening Project Workspace.

  • Break down work assigned to you

    If you are an assignee on a project task, you can create additional CWM tasks and stories under it directly from a Board. New items are automatically linked to the project task and its project.

  • Give project managers direct visibility

    Project managers see the CWM tasks and stories your team is executing directly under each project task on the planning page. They don't need Board access to review status, and a date-conflict indicator flags when a CWM item's planned dates fall outside the parent project task.

  • Share access through project permissions

    Users with read or write access to a project or project task can view and edit the linked CWM tasks, even without Board membership. Team leads and project stakeholders can act on connected work without being added to every Board.

When a project or project task is deleted

Deleting a project or a project task doesn’t delete the CWM tasks or stories connected to it. The connected CWM items stay on their Boards. Only the Project and Project task column values are cleared, and each affected item returns to the initial level on the Board.

A connected item doesn’t automatically return to its earlier parent. For example, in a Website rebuild project, the CWM task Draft homepage copy starts as a child of another CWM task, Content planning. You then reconnect Draft homepage copy to the project task Prepare launch content. If Prepare launch content is later deleted, Draft homepage copy stays on the Board but moves to the initial level as an independent task. It doesn’t return under Content planning.

What team members do in CWM

From within CWM, team members can perform the following actions:

Not every action is available on every project task. Assignee, hierarchy, and item-type conditions determine what’s allowed. For details, see Project task hierarchy and permissions in CWM.

What the project manager sees in Project Workspace

Project managers can enable the display of connected tasks in the Planner tab of a project in Project Workspace. When connected tasks display is enabled, the CWM tasks and stories linked to project tasks are shown as child items under each project task in the Planner. However, inline editing of these CWM child rows is not supported. Only the first level of the CWM hierarchy appears in the Planner.

When a linked CWM task has a start date earlier or an end date later than the project task, the date conflict is indicated in red on the connected task row. The indicator clears when the dates are corrected.

For information on enabling and using these views, see Project Workspace integration with CWM.

Access through project permissions

Users who have read or write access to a project or a project task, and have the sn_cwm.cwm_user role, can view and edit the connected CWM tasks. For more information, see Project task access in CWM.

Parent Topic:Using Collaborative Work Management